Program implementation process

Municipal electricity aggregation was enabled by the Massachusetts Restructuring Act of 1997 (Chapter 164, Section 134) and is regulated by the Massachusetts Department of Public Utilities (DPU). The implementation process includes a regulatory review and approval process that typically requires several months. The list below includes key milestones in the program implementation process.

1. Public vote

Wayland had to vote publicly to pursue aggregation.

  • The Town Meeting vote occurred on May 15, 2021.

2. Public review and comment

To obtain the necessary regulatory approval to launch Wayland Electricity Choice, the Town must first create an Aggregation Plan and make it available for public review and comment. The Aggregation Plan is a high-level authorization document that lays out the program structure and demonstrates how Wayland will meet regulatory requirements.

  • Wayland’s Aggregation Plan was presented to the public on October 17, 2022, and made available for a 30-day public review and comment period.

3. Regulatory review and approval

Wayland must submit its Aggregation Plan to the Massachusetts Department of Energy Resources (DOER) for review and then to the DPU for approval before the program can launch. This regulatory review process typically takes many months and can take as long as a year to complete.

  • Wayland’s Aggregation Plan was reviewed by DOER on November 14, 2022.
  • Wayland’s Aggregation Plan was submitted to the DPU on December 30, 2022.
  • Wayland’s Aggregation Plan was approved by the DPU on December 29, 2023.

4. Choosing an electricity supplier and signing an electricity supply contract

Once the regulatory review process is complete and Wayland’s Aggregation Plan has received approval from the DPU, Wayland implemented a public procurement process to select and sign a contract with an electricity supplier.

  • Wayland signed a 24-month electricity supply contract on February 28, 2024.

5. Public notification and education

After the electricity supply contract is signed, Wayland conducted a public education effort to inform the community about program details like price and renewable energy. This effort included public information sessions. In addition, a formal notification letter was sent from the Town to each electricity account holder who was eligible for automatic enrollment in the program. The letter included information about program options and prices and how to opt out if you do not want to participate.

  • Coming-Soon postcard mailing date: March 13, 2024.
  • Automatic enrollment notification mailing date: March 20, 2024.

6. Program launch

At the conclusion of the public education effort, Wayland Electricity Choice launched.

  • The program launched with May 2024 meter reads.